The R.M. of Sherwood has received an application to develop a Data Centre at the above-mentioned land. The proposed use is a permitted use under the Rural Municipality of Sherwood No. 159 Zoning Bylaw (Bylaw No. 18/17) and is accommodated under Section 8.1.2 – “Industry, Light”. Please see the attached executive summary submitted by the applicant for further details. The attached outline provides a summary of the documentation that will be formalized through a Development Agreement to be reviewed by the R.M of Sherwood Council on Monday, April 20, 2026.

Executive Summary

Conceptual Site Plan

Background Information:

At the Monday February 23rd, 2026, session of Regular R.M. of Sherwood Council a Multi-resident neighbouring property owner group provided a response to Council regarding the information presented at the February 9th, 2026, public hearing for Bylaw No. 01/26. Council included the submitted information for discussion to the agenda through the following resolution:

Resolution No. 
2026/0038
Approval of Agenda
Moved by: Councillor WilkeTHAT the agenda be adopted as amended by adding:8.2.2   Submission by Ratepayers – Bylaw No. 01/26

CARRIED UNANIMOUSLY

A concern noted by the group was the timeline for commenting on the future aspects of the proposed project. After the discussion, Council carried a motion creating the following resolution:

Resolution No. 
2026/0052
Submission by Ratepayers – Bylaw No. 01/26